Enabling Hydroelectric Generators to Connect to the National Grid
Industry
Hydropower
Location
Uganda
Capability
PLC Engineering & Grid Integration
The Challenge
Two 1.75 MW generators had originally been designed for island operation.
When grid-connected operation became necessary, the control system could not obtain the frequency information required to synchronise the generators with the National Grid.
The Response
Masisha worked with the facility’s technical team to develop PLC control logic that gradually adjusts generator speed.
The logic enables the generators to scan the expected frequency range until generator and grid frequency can be matched.
The Outcome
The new PLC control strategy enabled the generators to synchronise with the National Grid despite the original plant having been designed for island operation.